Amphitheater cost climbs to about $330 million as VENU turns to a $60 million land sale-leaseback

McKinney's council and its two development corporations on Monday let VENU sell the Sunset Amphitheater land to STORE Capital and lease it back; the city says no new public money is involved.

Cody Esparza

October 7, 20262 min read

Sunset Amphitheater - illustration, Jake Team LLC

The company building the 20,000-seat Sunset Amphitheater near U.S. 75 and State Highway 121 is raising another $60 million to finish it, and McKinney leaders signed off Monday on the deal that makes it possible.

In a joint meeting Oct. 5, the City Council and the boards of the McKinney Economic Development Corporation and McKinney Community Development Corporation took up an amended and restated incentive and development agreement with VENU Holding Corporation, the company formerly known as Notes Live, along with a separate protection agreement for the project.

The Dallas Morning News reported that the council voted to let the transaction go forward.

Why more money is needed

The project has grown since it was announced. "Originally it was about a $220 million project. Now we're at about $330 million," City Manager Paul Grimes said, according to The News. "They do have some financing challenges."

Robert Mudd, a VENU senior vice president, told the council that a statutory trust connected to the land did not work out as the company had expected, the paper reported. A company spokesperson declined to say more about it.

The company found another route through STORE Capital, a real estate investment trust based in Arizona. Under that arrangement, VENU sells the land, uses the proceeds to finish construction and then buys the property back next summer, after the venue opens. The original agreement restricts transfers of the property, so the deal required sign-off from the city and both corporations.

What the city says it got

City spokesperson Aschelle Morgan said VENU is still responsible for finishing and running the venue. "The $60 million from STORE Capital's purchase is private capital and does not represent any new public investment," she said in a statement quoted by The News.

The city says it added protections in the new agreement, among them caps on or cuts to some of VENU's incentives, added authority for the city to intervene, and an escrow account for construction money that the city manages.

Under the original 2024 agreement, VENU received reimbursements of sales and property taxes, $26 million in grant money and 46 acres.

A bigger venue

VENU says the amphitheater is about 70% complete and is scheduled to open between January and March 2027. Mudd said the expanded design adds climate control for summer and winter shows, setups for crowds from 5,000 to 20,000 people, and sound and lighting for immersive performances.

He told the council the changes could raise the number of shows to 100 a year, up from the 60 first planned, and push expected revenue to $164 million, compared with $98 million under the original plan. He said more than 90% of the suites, priced from $480,000 to $1.2 million, have been sold.

Sources

The Dallas Morning News

legistar1.granicus.com

legistar1.granicus.com

Share

Cody Esparza

Cody Esparza covers McKinney city hall, the council, and county government.

Related Stories

More in Texas