Rebuild of McMakin Street and Finch Avenue in east McKinney, with new drainage and sidewalks, filed with the state at $4.5 million

Construction is scheduled from May 2027 to April 2028 under a state filing registered Tuesday. The design grew after the council told staff to add sidewalks to every street reconstruction.

Cody Esparza· AI-assisted, edited by Jake Team

October 16, 20262 min read

McKinney street rebuild - illustration, Jake Team LLC

Two east McKinney streets are scheduled to be torn up and rebuilt with new drainage and sidewalks starting next spring, according to a city project registered with the state this week.

A Texas Department of Licensing and Regulation record dated Tuesday, Oct. 13, puts the cost of the East McKinney Drainage Study and Improvements project at $4,514,000. It covers roadway, pedestrian and drainage work in two stretches:

  • McMakin Street from McDonald Street to Fowler Street
  • Finch Avenue from Hunt Street to Greenwood Road

The city is the owner and the money is public, the registration shows. Construction is set to begin May 1, 2027, and wrap up by April 1, 2028. Pape-Dawson is listed as the designer.

Why the design grew

The engineering firm has been working on the project for the city for some time. In July 2025 the City Council approved raising the cap on Pape-Dawson's design contract from $790,000 to $1,024,000, according to the staff report for that vote, which passed.

The report said the council had directed after the original contract was signed that sidewalks be added to all street reconstruction projects. That change, along with what the firm's drainage study turned up, added work: adjusting the road's vertical profile to fix drainage problems, building the sidewalk, and narrowing the existing pavement in some spots to make room for it.

The added drainage work also meant more land rights. The contract had assumed four easement documents, but staff said eight more would be needed for temporary construction easements and permanent drainage easements. The firm was also to do more underground utility mapping to keep the work from running into existing lines.

The state registration is an early step; it does not name a construction contractor, and the city has not yet put a construction contract before the council.

Sources

State of Texas

webapi.legistar.com

webapi.legistar.com

Share

Cody Esparza· AI-assisted, edited by Jake Team

Cody Esparza covers McKinney city hall, the council, and county government.

Related Stories

More in Texas