The City of McKinney has registered a $10.1 million project to replace water and wastewater mains and rebuild pavement on four streets near College Street, according to a filing with the Texas Department of Licensing and Regulation dated Monday.
The state accessibility registration names the project "FY-22 Main Replacement & Street Repair" and lists College Street, Hunt Street, Davis Street and Church Street as the facility, with an address of 200 S. College St. It gives a start date of March 1, 2027, and a completion date of July 1, 2028, and says the work involves public funds on public land.
What would be built
The filing's scope of work lists:
- 3,615 linear feet of 8-inch wastewater line
- 3,890 linear feet of 8-inch water line
- 3,110 linear feet of 12-inch water line
- Pavement replacement
- Storm sewer improvements
Together the new water and wastewater lines add up to about 10,600 feet, or roughly 2 miles. The registration lists LJB Engineering of Richardson as the design firm and the City of McKinney as owner.