Erosion has left a stretch of 27-inch sewer line exposed over Stover Creek, and a design contract is up Tuesday

Council votes Nov. 17 on a $443,250 Halff Associates contract to design a permanent repair for about 200 feet of exposed line near County Roads 124 and 161. Construction would start in late 2027.

Cody Esparza· AI-assisted, edited by Jake Team

November 15, 20262 min read

McKinney City Council - illustration, Jake Team LLC

About 200 feet of a large sewer line that crosses Stover Creek is now sitting out in the open, and the city wants to start designing a permanent fix.

The City Council will vote Tuesday, Nov. 17, on a $443,250 engineering contract with Halff Associates for the Stover Creek Aerial Wastewater Line Permanent Repair Project. The resolution would let the city spend up to $490,000 with the firm if the scope shifts during design or construction.

What inspectors found

According to the staff report, recent inspections found roughly 200 linear feet of the 27-inch line exposed and vulnerable because erosion has worn away the ground around it. The pipe spans the creek roughly 600 yards from where County Road 124 meets County Road 161, on the northwest side.

The project would replace the exposed section and encase it, protecting the pipe from the weather and from possible damage or tampering by people who reach the creek. Crews would also stabilize the creek banks to slow further erosion.

Cost and timing

Halff's early estimate puts construction at about $1.52 million. Its fee covers $300,400 in basic design and bidding work and $142,850 in other services, including construction administration, surveying, geotechnical and environmental work, easement documents and utility coordination.

Design should take about nine months, with construction expected to begin in late 2027, the report says. The money comes from the city's capital improvement program, and about $3.41 million would remain in the project account after the contract.

Halff was one of six firms the council shortlisted in September 2024 for drainage and floodplain work.

More pipe work on the same agenda

A separate item would hire Freese and Nichols for $363,120, with a cap of $400,000, to design the city's fiscal 2027 water and wastewater main project. Inspections flagged about 19,760 feet of water lines and 16,980 feet of sewer mains for rehabilitation or replacement, with construction estimated at about $7.65 million and starting as soon as mid-2027.

The regular meeting begins at 6 p.m.

Sources

webapi.legistar.com

webapi.legistar.com

legistar1.granicus.com

Share

Cody Esparza· AI-assisted, edited by Jake Team

Cody Esparza covers McKinney city hall, the council, and county government.