Surprises underground push the police gun range building to the edge of its $1.38 million budget

Council's consent agenda Tuesday adds $75,000 for builder Crossland and $15,000 for architect Conduit after unexpected site conditions forced changes to civil plans, piers and water lines. About $5,184 would be left.

Cody Esparza· AI-assisted, edited by Jake Team

November 16, 20262 min read

McKinney City Council - illustration, Jake Team LLC

A new support building at the McKinney Police Department's gun range has run into unexpected site conditions, and the City Council is being asked Tuesday to add $90,000 to the job.

Two related resolutions sit on the consent agenda for the council's Nov. 17 regular meeting, which starts at 6 p.m.

What is being built

The project calls for a storage and workshop building of about 2,400 square feet, with restrooms, plus replacement of the pavement at the range. The council approved a guaranteed maximum price contract of up to $1,119,956 with Crossland Construction Company on May 19, with completion expected in May 2027.

According to city staff, work in the field turned up conditions nobody planned for, requiring adjustments to the civil plans, the structural piers, and the water and irrigation systems.

Why the contingency is needed now

To keep the project inside its approved budget, the original Crossland contract carried no owner's contingency, staff wrote. Extra work so far has been paid from the contractor's own contingency. The first resolution, capped at $75,000, would refill that and create an owner's contingency for whatever else comes up.

The second would add $12,500 in design work for Conduit Architecture + Design, the McKinney firm that drew the building, plus a $2,500 contingency, for a total of up to $15,000. Conduit's contract would rise to $110,750. Conduit was one of five firms the city placed in a pre-qualified pool for facilities projects in 2025.

Little room left

The project budget is $1,378,712. With both changes, staff project expenses of $1,373,528, including materials testing by Terracon, commissioning, geotechnical work and an owner's representative. That would leave $5,184 in the project account.

Also Tuesday: drive-through restaurants

Elsewhere on the agenda, staff recommends tabling a request for a permit that would allow three drive-through restaurants, a Burger King, a Popeyes and a Taco Bueno, along West University Drive just west of Aviation Way. Planning commissioners unanimously recommended denial on Oct. 27, 7-0. Staff wants the hearing continued to Dec. 1.

Sources

webapi.legistar.com

webapi.legistar.com

webapi.legistar.com

webapi.legistar.com

legistar1.granicus.com

Share

Cody Esparza· AI-assisted, edited by Jake Team

Cody Esparza covers McKinney city hall, the council, and county government.

Related Stories

More in Texas