Silverado Trail's missing westbound lanes and Rowlett Creek bridge are now set for 2027-28 construction, state filing shows

A state registration filed Nov. 11 puts the $4.7 million widening between Kenley and Burnett drives on a September 2027 start, about two years later than the city's 2024 timeline and above its early cost estimate.

Cody Esparza· AI-assisted, edited by Jake Team

November 17, 20262 min read

The long-planned fix for a short gap on Silverado Trail in southwest McKinney now has construction dates on file with the state, and they are later than the city first expected.

A Texas Department of Licensing and Regulation project registration filed Nov. 11 says work on two more travel lanes for Silverado Trail, a two-lane bridge and other road work will start Sept. 1, 2027, and finish Sept. 1, 2028. The filing estimates the cost at $4.7 million and identifies the job as publicly funded.

What is being built

City Council records describe the project, known as Silverado Trail Lanes 3 & 4, as roughly 570 feet of new westbound lanes from Kenley Drive to Burnett Drive. The centerpiece is a bridge about 180 feet long over Rowlett Creek, carrying a sidewalk and linking to the creekside trail that runs beneath it.

A 30-inch North Texas Municipal Water District sewer line has to be moved out of the way for the bridge.

When the council hired Halff Associates to design it in May 2024, staff put the preliminary construction cost at $3,570,281 and said construction could begin in late 2025, after about 15 months of design.

What changed

In April, the council added work to Halff's contract to file a Conditional Letter of Map Revision with FEMA, a step that revises the mapped floodplain along Rowlett Creek before building in it. That raised the design contract's cap from $900,000 to $950,000, and staff said design was expected to wrap up by September 2026.

The project is funded through the city's capital improvements program under project ST2013.

A Parks and Recreation project tracker in Thursday's McKinney Community Development Corporation board packet lists the Silverado lanes and trail work as still in design.

The state filing does not say whether a construction contract has been bid, and no award has appeared on a council agenda.

Sources

State of Texas

webapi.legistar.com

webapi.legistar.com

legistar1.granicus.com

Share

Cody Esparza· AI-assisted, edited by Jake Team

Cody Esparza covers McKinney city hall, the council, and county government.

Related Stories

More in Texas