The long-planned fix for a short gap on Silverado Trail in southwest McKinney now has construction dates on file with the state, and they are later than the city first expected.
A Texas Department of Licensing and Regulation project registration filed Nov. 11 says work on two more travel lanes for Silverado Trail, a two-lane bridge and other road work will start Sept. 1, 2027, and finish Sept. 1, 2028. The filing estimates the cost at $4.7 million and identifies the job as publicly funded.
What is being built
City Council records describe the project, known as Silverado Trail Lanes 3 & 4, as roughly 570 feet of new westbound lanes from Kenley Drive to Burnett Drive. The centerpiece is a bridge about 180 feet long over Rowlett Creek, carrying a sidewalk and linking to the creekside trail that runs beneath it.
A 30-inch North Texas Municipal Water District sewer line has to be moved out of the way for the bridge.
When the council hired Halff Associates to design it in May 2024, staff put the preliminary construction cost at $3,570,281 and said construction could begin in late 2025, after about 15 months of design.
What changed
In April, the council added work to Halff's contract to file a Conditional Letter of Map Revision with FEMA, a step that revises the mapped floodplain along Rowlett Creek before building in it. That raised the design contract's cap from $900,000 to $950,000, and staff said design was expected to wrap up by September 2026.